Friday, May 7, 2010

Hard Deadline

Going through some of the documents, it turns out that the community is up
against a hard deadline.

The Texas Commission on Environmental Quality (TCEQ) has required that we
file an Emergency Action Plan (EAP) on or before January 1, 2011.

Part of the EAP is An inundation map showing the at risk houses. This is
also part of the Hydrologic and Hydraulic Analysis (H&H) which is also
required to develop the Plans & Specifications (P&S) for the dam repair.


http://www.tceq.state.tx.us/assets/public/compliance/field_ops/damsafety/gi-
394.doc

Tuesday, May 4, 2010

Zimmerhansel Dam Meeting

There were a lot of requests this evening at the special meeting for some of
the documentation regarding the Zimmerhansel Dam.

Below are the links for all of the relevant documents.

Original 2005 Inspection Report

Revised 2009 Inspection Report


Some background documents


Dam Removal Guidelines

Hydrologic and Hydraulic Guidelines for Dams in Texas

Guidelines For Operation And Maintenance Of Dams In Texas

TCEQ Guidelines on Dams